Commercial EV Charging Case Study         
    
    Installation of 5 FLO CORE+ (MAX) EV chargers From main EV electrical room, pull power from the main switch and install a dedicated EV distribution panel for all EV chargers.         
    
                  
            
            
            
            
            City Electrical Permit Application
Electrical Inspection 
City Final inspections
         
            
            
            Installation of 5 FLO CORE+ (MAX) EV chargers From main EV electrical room, pull power from the main switch and install a dedicated EV distribution panel for all EV chargers. 
Charging stations are located the other side of the building, roughly 150 ~ 180 meters away. 
Each EV charger uses 100 AMP circuit breakers, therefore, #2/0 AWG copper RW 90 cable will be needed. Coring & X-Ray and mounting EV chargers on the wall with cord management system. 
Mounting of bollard in front of the pedestals.